Difference between cost plan and budget
It is important not to confuse cost plans and budgets.
A budget is a statement of the amount of money available to spend over a period of time, or on a specific thing, such as a building. The budget is set by the client (although they make seek help to do this). It may include an outline plan for how that money will be spent, and a breakdown of the items it will be spent on. Budgets set a limit for expenditure and this can help determine what is affordable. They should be set as early as possible so that expectations can be managed. It is important that they are based on evidence and that they are realistic, rather than simply stating the amount of money available, or being a wild guess, because, once the budget is set in people's minds, it can be very difficult to change.
For more information see: Budget.
Cost plans are typically prepared by a cost consultant and provide an estimate of what the actual costs are likely to be. Cost plans evolve through the life of the project, developing in detail and accuracy as more information becomes available about the nature of the project. They can range from very early initial cost appraisals through to tender pricing documents and the final account. If the cost plan exceeds the budget, it may be necessary to reduce the cost or scope of the project.
For more information see: Cost plan.
[edit] Related articles on Designing Buildings
- Budget.
- Capital costs for construction projects.
- Construction costs.
- Cost control.
- Cost plans for construction projects.
- Cost management techniques used to monitor the cost of construction projects.
- Difference between collateral warranties and third party rights.
- Difference between preliminaries and preambles
- Elemental cost plan for design and construction.
- Final account.
- Outturn cost.
- Quantity surveyor.
- Tender pricing document.
Featured articles and news
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties at 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.